Requirements for the construction of FRP marker posts:
1. The construction is ideal in an environment where the temperature and temperature are not lower than 5 degrees Celsius.
2. The construction road surface must be clean, dry and flat.
3. When the flatness of the construction road is poor, you can use asphalt or cement mortar to lay it flat. However, it must be more solid and dry before construction.
4. Wet roads cannot be constructed.
5. After the rain, it is necessary to wait until the road is abundant and dry before construction. Generally, the construction should be more than 24 hours.
There are many contents on the pile body, and its content is roughly divided into internal and external information, and external information is the fundamental purpose of product installation. Therefore, it must include the type of the pipeline, the name of the unit to which it belongs, the warning language and the contact number of the report. It is stated that the name of the unit to which the pipeline belongs and the contact number are to facilitate other construction teams to contact their affiliated company during construction or when an accident occurs (for example, the buried pipeline is damaged) and citizens can notify the pipeline owner in time. Warning words can include "cable pipelines, excavation is strictly prohibited" and other contents, which play a role in warning others. The internal information includes marker posts, pipeline area names, enterprise logos, etc. This content is to facilitate the future inspection work of the company's employees, and the company can control it by itself, and do not make strict requirements.